VANCOUVER, April 2, 2012 /CNW/ - Silver Wheaton Corp. ("Silver Wheaton"
or the "Company") (TSX:SLW)(NYSE:SLW) is pleased to announce end-of-year 2011 attributable proven and probable reserves of 798
million ounces of silver and 0.22 million ounces of gold, attributable
measured and indicated resources of 452 million ounces of silver and
0.38 million ounces of gold, and attributable inferred resources of 355
million ounces of silver and 0.07 million ounces of gold.
During 2011, attributable proven and probable reserves decreased by 144
million ounces of silver and 0.03 million ounces of gold, attributable
measured and indicated resources increased by 86 million ounces of
silver and 0.14 million ounces of gold, and attributable inferred
resources decreased by 139 million ounces of silver and increased by
0.02 million ounces of gold.
Silver Wheaton's decrease in 2011 attributable reserves was due in part
to depletion from record production over the year, as well as a
reduction in silver reserves at Goldcorp Inc.'s ("Goldcorp") Peñasquito
mine and Primero Mining Corp.'s ("Primero") San Dimas mine.
As per Goldcorp's February 15, 2012, disclosure, the reduction in silver
reserves at Peñasquito occurred as a result of increased cut-off grades
due to higher operating costs than those estimated in the original 2006
feasibility study. In 2012, exploration at Peñasquito will target
additional high-grade mineralization in mantos beneath the open pit
bottoms, in addition to testing the potential for block cave mining of
deep mineralized zones.
As per Primero's March 28, 2012, disclosure, in an effort to improve
mine planning and expand long-term production levels at its San Dimas
mine, Primero elected to utilize block modeling to estimate its mineral
reserves and resources rather than the polygonal method, which it had
used historically. The estimates made using this new approach resulted
in a reduction in both silver reserves and inferred resources at the
San Dimas mine, as of December 31, 2011. The updated mineral reserve
and resource estimates for San Dimas have been prepared by AMC Mining
Consultants (Canada) Ltd. and a 43-101 technical report is expected to
be filed on SEDAR within 45 days.
Primero's disclosure also states that there is significant exploration
potential at San Dimas beyond the stated mineral reserves and
resources, some of which has been reported as mineral potential.
Further details can be found in their March 28, 2012, disclosure.
Primero believes that the new estimation approach will improve mine
planning, and that further drilling and mine development will result in
mineral resources being converted to mineral reserves, a reasonable
amount of the exploration potential being converted to inferred
resources, and new mineral discoveries being realized.
"Silver Wheaton continues to have nearly twice the silver reserves of
any other silver company in the world," said
Randy Smallwood
, Silver
Wheaton's President and Chief Executive Officer. "We are in a period
where commodity price gains are often largely offset by industry wide
operating cost pressures, which can result in reserve reductions. In an
inflationary environment such as this, the strength of our 'fixed
operating cost' business model, which continues to generate amongst the
highest cash operating margins in the precious metals industry, is
apparent. Our core assets are mainly comprised of long-life and
lower-cost mines, with proven records of reserve replacement and
resource conversion, and we are confident that ongoing exploration
programs will continue this trend well into the future."
"San Dimas has produced in excess of 580 million ounces of silver in its
greater than 100 years of operation and aggressive exploration,
particularly in the Sinaloa Graben region, continues to yield excellent
results. We are confident that San Dimas will deliver solid production
results, and that Primero's efforts to improve mine planning will
ultimately add value to this impressive asset, including the potential
for significantly expanded long-term production levels."
The tables below set forth the estimated Mineral Reserves and Mineral
Resources (silver only, except where a purchase agreement includes
gold) for the mines relating to which the Company has purchase
agreements, adjusted where applicable to reflect the Company's
percentage entitlement to silver and/or gold produced from such mines,
as of December 31, 2011, unless otherwise noted. The tables are based
on information available to the Company as of the date of this document
and have been updated from the Company's most recently filed Annual
Information Form and Management Discussion and Analysis for the year
ended December 31, 2011. The most current Mineral Reserves and Mineral
Resources will be available on the Company's website.
ATTRIBUTABLE PROVEN AND PROBABLE RESERVES (1,2,3,8,15,16)
AS OF DECEMBER 31, 2011 UNLESS OTHERWISE NOTED (6)
|
|
|
|
|
|
|
|
|
|
|
|
As of
December 31,
2011 unless
otherwise
noted(6)
|
Proven
|
Probable
|
Proven Probable
|
|
|
Tonnage
|
Grade
|
Contained
|
Tonnage
|
Grade
|
Contained
|
Tonnage
|
Grade
|
Contained
|
Process
Recovery(7)
|
|
Mt
|
g/t
|
Moz
|
Mt
|
g/t
|
Moz
|
Mt
|
g/t
|
Moz
|
%
|
|
SILVER
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Peñasquito (25%)
|
|
|
|
|
|
|
|
|
|
|
|
Mill
|
156.6
|
28.9
|
145.5
|
129.3
|
20.2
|
83.8
|
285.9
|
24.9
|
229.3
|
53-65%
|
|
Heap Leach
|
8.3
|
14.4
|
3.9
|
23.0
|
9.4
|
6.9
|
31.4
|
10.7
|
10.8
|
24%
|
|
San Dimas(10)
|
-
|
-
|
-
|
3.5
|
281.5
|
31.8
|
3.5
|
281.5
|
31.8
|
94%
|
|
Pascua-Lama (25%)
|
9.9
|
59.5
|
18.9
|
86.3
|
54.1
|
150.2
|
96.2
|
54.7
|
169.1
|
82%
|
|
Lagunas Norte(11)
|
3.3
|
3.2
|
0.3
|
37.6
|
3.2
|
3.9
|
40.9
|
3.2
|
4.2
|
22%
|
|
Pierina(11)
|
2.1
|
19.9
|
1.3
|
18.9
|
10.8
|
6.6
|
21.0
|
11.8
|
8.0
|
37%
|
|
Veladero(11)
|
3.7
|
13.4
|
1.6
|
61.3
|
13.4
|
26.5
|
65.0
|
13.4
|
28.1
|
6%
|
|
Yauliyacu(12)
|
1.0
|
99.6
|
3.3
|
2.7
|
105.9
|
9.1
|
3.7
|
104.2
|
12.4
|
85%
|
|
Neves-Corvo
|
|
|
|
|
|
|
|
|
|
|
|
Copper
|
23.2
|
44.0
|
32.9
|
4.5
|
45.0
|
6.5
|
27.7
|
44.2
|
39.4
|
35%
|
|
Zinc
|
19.4
|
67.0
|
41.7
|
3.8
|
64.0
|
7.8
|
23.1
|
66.5
|
49.5
|
23%
|
|
Rosemont(13)
|
128.8
|
4.5
|
18.5
|
366.8
|
3.8
|
44.5
|
495.6
|
3.9
|
62.9
|
80%
|
|
Mineral Park(13)
|
293.9
|
2.7
|
25.7
|
74.5
|
2.9
|
7.0
|
368.4
|
2.8
|
32.6
|
49%
|
|
Zinkgruvan
|
|
|
|
|
|
|
|
|
|
|
|
Zinc
|
8.2
|
103.0
|
27.2
|
2.4
|
60.0
|
4.7
|
10.7
|
93.1
|
31.9
|
70%
|
|
Copper
|
2.8
|
32.0
|
2.8
|
0.1
|
29.0
|
0.1
|
2.8
|
31.9
|
2.9
|
78%
|
|
Aljustrel
|
|
|
|
|
|
|
|
|
|
|
|
Copper
|
2.2
|
19.2
|
1.3
|
8.4
|
15.3
|
4.1
|
10.6
|
16.1
|
5.5
|
30%
|
|
Campo Morado (75%)
|
0.7
|
166.7
|
3.8
|
0.1
|
123.4
|
0.3
|
0.8
|
162.6
|
4.1
|
55%
|
|
Stratoni
|
1.7
|
174.0
|
9.3
|
0.1
|
225.0
|
0.7
|
1.8
|
177.0
|
10.0
|
84%
|
|
Minto
|
5.5
|
5.4
|
1.0
|
5.9
|
4.6
|
0.9
|
11.4
|
5.0
|
1.8
|
80%
|
|
Cozamin(14)
|
|
|
|
|
|
|
|
|
|
|
|
Copper
|
0.9
|
63.0
|
1.7
|
4.9
|
50.7
|
8.0
|
5.8
|
52.5
|
9.8
|
74%
|
|
Los Filos
|
81.0
|
5.2
|
13.5
|
231.2
|
5.4
|
40.2
|
312.2
|
5.3
|
53.610
|
5%
|
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL SILVER
|
|
|
354.1
|
|
|
443.5
|
|
|
797.6
|
|
|
GOLD
|
|
|
|
|
|
|
|
|
|
|
|
Minto
|
5.5
|
0.69
|
0.12
|
5.9
|
0.51
|
0.10
|
11.4
|
0.60
|
0.22
|
74%
|
|
TOTAL GOLD
|
|
0.12
|
|
0.10
|
|
|
0.22
|
|
ATTRIBUTABLE MEASURED INDICATED RESOURCES (1,2,3,4,5,9,15,16)
AS OF DECEMBER 31, 2011 UNLESS OTHERWISE NOTED (6)
|
|
|
|
|
|
|
|
|
|
|
As of
December 31,
2011 unless
otherwise
noted(6)
|
Measured
|
Indicated
|
Measured Indicated
|
|
Tonnage
|
Grade
|
Contained
|
Tonnage
|
Grade
|
Contained
|
Tonnage
|
Grade
|
Contained
|
|
Mt
|
g/t
|
Moz
|
Mt
|
g/t
|
Moz
|
Mt
|
g/t
|
Moz
|
|
SILVER
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Peñasquito (25%)
|
|
|
|
|
|
|
|
|
|
|
Mill
|
34.1
|
13.1
|
14.4
|
128.2
|
12.4
|
51.1
|
162.3
|
12.6
|
65.5
|
|
Heap Leach
|
1.0
|
4.6
|
0.2
|
6.2
|
3.9
|
0.8
|
7.2
|
4.0
|
0.9
|
|
Pascua-Lama (25%)
|
5.3
|
24.5
|
4.2
|
55.9
|
23.4
|
42.1
|
61.2
|
23.5
|
46.3
|
|
Yauliyacu(12)
|
0.7
|
108.5
|
2.5
|
6.1
|
192.4
|
37.8
|
6.8
|
183.5
|
40.3
|
|
Neves-Corvo
|
|
|
|
|
|
|
|
|
|
|
Copper
|
15.4
|
53.0
|
26.2
|
3.4
|
51.2
|
5.6
|
18.8
|
52.7
|
31.8
|
|
Zinc
|
42.7
|
54.3
|
74.6
|
14.5
|
49.5
|
23.0
|
57.2
|
53.1
|
97.6
|
|
Rosemont(13)
|
7.2
|
3.9
|
0.9
|
103.0
|
2.7
|
8.8
|
110.2
|
2.7
|
9.7
|
|
Mineral Park(13)
|
101.0
|
2.6
|
8.4
|
175.6
|
2.7
|
15.2
|
276.6
|
2.7
|
23.6
|
|
Zinkgruvan
|
|
|
|
|
|
|
|
|
|
|
Zinc
|
0.9
|
123.4
|
3.8
|
3.3
|
109.5
|
11.5
|
4.2
|
112.6
|
15.2
|
|
Copper
|
2.7
|
24.4
|
2.1
|
0.1
|
38.5
|
0.1
|
2.8
|
24.9
|
2.2
|
|
Aljustrel
|
|
|
|
|
|
|
|
|
|
|
Zinc
|
1.3
|
65.6
|
2.7
|
20.5
|
60.3
|
39.7
|
21.8
|
60.7
|
42.4
|
|
Copper
|
-
|
-
|
-
|
0.1
|
11.7
|
0.04
|
0.1
|
11.7
|
0.04
|
|
Campo Morado (75%)
|
2.1
|
162.1
|
10.8
|
4.4
|
158.0
|
22.5
|
6.5
|
159.3
|
33.2
|
|
Loma de La Plata (12.5%)
|
-
|
-
|
-
|
3.6
|
169.0
|
19.8
|
3.6
|
169.0
|
19.8
|
|
Minto
|
9.4
|
3.9
|
1.2
|
27.2
|
3.2
|
2.8
|
36.5
|
3.3
|
3.9
|
|
Keno Hill (25%)
|
|
|
|
|
|
|
|
|
|
|
Underground
|
-
|
-
|
-
|
0.3
|
545.4
|
4.5
|
0.3
|
545.4
|
4.5
|
|
Elsa Tailings
|
-
|
-
|
-
|
0.6
|
119.0
|
2.4
|
0.6
|
119.0
|
2.4
|
|
Los Filos
|
7.9
|
9.5
|
2.4
|
42.7
|
7.2
|
9.9
|
50.6
|
7.6
|
12.4
|
|
|
|
|
|
|
|
|
|
|
|
|
TOTAL SILVER
|
|
|
154.2
|
|
|
297.6
|
|
|
451.8
|
|
GOLD
|
|
|
|
|
|
|
|
|
|
|
Minto
|
9.4
|
0.44
|
0.13
|
27.2
|
0.28
|
0.24
|
36.5
|
0.32
|
0.38
|
|
TOTAL GOLD
|
|
0.13
|
|
|
0.24
|
|
|
0.38
|
ATTRIBUTABLE INFERRED RESOURCES (1,2,3,4,5,9,15,16)
AS OF DECEMBER 31, 2011 UNLESS OTHERWISE NOTED (6)
|
|
|
|
|
As of
December 31,
2011 unless
otherwise
noted(6)
|
Inferred
|
|
|
Tonnage
|
Grade
|
Contained
|
|
Mt
|
g/t
|
Moz
|
|
SILVER
|
|
|
|
|
|
|
|
|
|
Peñasquito (25%)
|
|
|
|
|
Mill
|
36.7
|
8.8
|
10.4
|
|
Heap Leach
|
14.1
|
1.7
|
0.8
|
|
San Dimas(10)
|
5.8
|
324.0
|
60.8
|
|
Pascua-Lama (25%)
|
8.1
|
15.5
|
4.0
|
|
Yauliyacu(12)
|
13.8
|
163.5
|
72.7
|
|
Neves-Corvo
|
|
|
|
|
Copper
|
28.5
|
40.0
|
36.6
|
|
Zinc
|
33.0
|
55.0
|
58.3
|
|
Rosemont(13)
|
163.0
|
2.1
|
11.2
|
|
Mineral Park(13)
|
320.1
|
2.3
|
23.9
|
|
Zinkgruvan
|
|
|
|
|
Zinc
|
5.6
|
69.0
|
12.4
|
|
Copper
|
0.8
|
36.0
|
0.9
|
|
Aljustrel
|
|
|
|
|
Zinc
|
8.7
|
50.4
|
14.0
|
|
Copper
|
4.7
|
16.0
|
2.4
|
|
Campo Morado (75%)
|
2.4
|
117.3
|
9.1
|
|
Stratoni
|
0.7
|
217.0
|
4.7
|
|
Loma de La Plata (12.5%)
|
0.2
|
76.0
|
0.4
|
|
Minto
|
8.5
|
2.9
|
0.8
|
|
Keno Hill (25%)
|
|
|
|
|
Underground
|
0.1
|
340.1
|
1.4
|
|
Los Filos
|
158.4
|
5.9
|
29.9
|
|
|
|
|
|
|
TOTAL SILVER
|
|
|
354.6
|
|
GOLD
|
|
|
|
|
Minto
|
8.5
|
0.24
|
0.07
|
|
TOTAL GOLD
|
|
0.07
|
|
Notes:
|
|
1.
|
All Mineral Reserves and Mineral Resources have been calculated in
accordance with the CIM Standards and NI 43-101, or the AusIMM JORC
equivalent.
|
|
2.
|
Mineral Reserves and Mineral Resources are reported above in millions of
metric tonnes ("Mt"), grams per metric tonne ("g/t") and millions of
ounces ("Moz").
|
|
3.
|
Individual qualified persons ("QPs"), as defined by the NI 43-101, for
the Mineral Reserve and Mineral Resource estimates are as follows:
|
|
|
a.
|
Peñasquito - Maryse Belanger, P.Geo. (Vice President, Technical
Services, Goldcorp Inc.)
|
|
|
b.
|
San Dimas -Rodney Webster, MAusIMM MAIG (Geology Manager, Principal
Geologist), Herbert A. Smith, P.Eng (Mining Manager, Principal Mining
Engineer) and J. Morton Shannon, P.Geo (Geology Manager, Principal
Geologist) all employees of AMC Mining Consultants (Canada) Ltd.
|
|
|
c.
|
Pascua-Lama - Dino Pilotto, P.Eng. (Principal Mining Consultant, SRK
Consulting (Canada) Inc.); and Bart A. Stryhas, Ph.D., CPG (Principal
Resource Geologist, SRK Consulting (U.S.) Inc.)
|
|
|
d.
|
Yauliyacu - Neil Burns, M.Sc., P.Geo. (Vice President, Technical
Services); and Samuel Mah, M.A.Sc., P.Eng. (Director of Engineering),
both employees of the Company (the "Company's QPs")
|
|
|
The Company's QPs are responsible for overall corporate review and all
other operations and development projects.
|
|
4.
|
The Mineral Resources reported in the above tables are exclusive of
Mineral Reserves. The San Dimas, Minto, Campo Morado, Neves-Corvo,
Zinkgruvan and Aljustrel mines report Mineral Resources inclusive of
Mineral Reserves. The Company's QPs have made the exclusive Mineral
Resource estimates for these mines based on average mine recoveries and
dilution.
|
|
5.
|
Mineral Resources which are not Mineral Reserves do not have
demonstrated economic viability.
|
|
6.
|
Other than as detailed below, Mineral Reserves and Mineral Resources are
reported as of December 31, 2011 based on information available to the
Company as of the date of this document, and therefore will not reflect
updates, if any, after such date. The most current Mineral Reserves
and Mineral Resources will be available on the Company's website.
|
|
|
a.
|
Resources and Reserves for Yauliyacu, Neves-Corvo and Zinkgruvan are
reported as of June 30, 2011.
|
|
|
b.
|
Resources for Rosemont are reported as of October 22, 2008 and Reserves
as of March 17, 2009.
|
|
|
c.
|
Resources for Mineral Park are reported as of December 29, 2006.
|
|
|
d.
|
Resources and Reserves for Aljustrel's Feitais and Moinho deposits are
reported as of November 30, 2010, Resources for the Estaçao deposit are
reported as of December 31, 2007.
|
|
|
e.
|
Resources for Campo Morado's El Rey, Naranjo and Reforma deposits are
reported as of October 13, 2005.
|
|
|
f.
|
Resources and Reserves for Stratoni are reported as of August 10, 2010.
|
|
|
g.
|
Resources for Keno Hill's Lucky Queen and Onek deposits are reported as
of June 30, 2011 and Elsa Tailings as of April 22, 2010.
|
|
|
h.
|
Resources for Loma de La Plata are reported as of May 20, 2009.
|
|
7.
|
Process recoveries are the average percentage of silver in a saleable
product (doré or concentrate) recovered from mined ore at the
applicable site process plants as reported by the operators.
|
|
8.
|
Mineral Reserves are estimated using appropriate process recovery rates
and commodity prices of $20.00 per ounce of silver, unless otherwise
noted below:
|
|
|
a.
|
Pascua-Lama, Lagunas Norte, Veladero and Pierina - $22.00 per ounce.
|
|
|
b.
|
Yauliyacu - $30.00 per ounce.
|
|
|
c.
|
Neves-Corvo - 1.4% Cu cut-off for the copper Reserve and 5.0% Zn cut-off
for the all zinc Reserves except for Lombador which was reported above
a cut-off of 6.0% Zn.
|
|
|
d.
|
Rosemont -$10.00 per ounce.
|
|
|
e.
|
Mineral Park - $7.50 per ounce.
|
|
|
f.
|
Zinkgruvan - 3.7% Zn equivalent cut-off for the zinc Reserve and 1.8% Cu
cut-off for the copper Reserve.
|
|
|
g.
|
Aljustrel - 1.5% Cu cut-off for all copper Reserves, 4.5% Zn cut-off for
all zinc Reserves.
|
|
|
h.
|
Campo Morado - $30.00 per ounce.
|
|
|
i.
|
Minto - $3.90 per ounce silver and $300 per ounce gold.
|
|
9.
|
Mineral Resources are estimated using appropriate recovery rates and
commodity prices of $24.00 per ounce of silver, unless otherwise noted
below:
|
|
|
a.
|
San Dimas -$25.00 per ounce.
|
|
|
b.
|
Pascua-Lama, Lagunas Norte, Veladero and Pierina - $28.00 per ounce.
|
|
|
c.
|
Yauliyacu - $30.00 per ounce.
|
|
|
d.
|
Neves-Corvo - 1.0% Cu cut-off for the copper Resource and 3.0% Zn
cut-off for the zinc Resource.
|
|
|
e.
|
Rosemont - 0.2% Cu cut-off.
|
|
|
f.
|
Zinkgruvan - 3.1% Zn equivalent cut-off for the zinc Resource and 1.5%
Cu cut-off for the copper Resource.
|
|
|
g.
|
Mineral Park - $7.50 per ounce.
|
|
|
h.
|
Aljustrel - 1.5% Cu cut-off for all copper Resources, 4.5% Zn cut-off
for Feitais and Moinho zinc Resources and 4.0% for Estação zinc
Resources.
|
|
|
i.
|
Campo Morado - $30.00 per ounce for the G-9 zones and 5% Zn cut-off for
the El Rey, Naranjo and Reforma deposits.
|
|
|
j.
|
Loma de La Plata - $12.50 per ounce
|
|
|
k.
|
Minto - 0.5% Cu cut-off.
|
|
|
l.
|
Keno Hill - $15.25 per ounce for the Southwest and 99 Zones, $14.50 per
ounce for the East Zone, $17.00 per ounce for the Elsa Tailings and
$18.50 per ounce for the Lucky Queen and Onek deposits.
|
|
10.
|
The San Dimas purchase agreement provides that from August 6, 2010 until
August 5, 2014, Primero Mining Corp. ("Primero") will deliver to the
Company a per annum amount equal to the first 3.5 million ounces of
payable silver produced at San Dimas and 50% of any excess, plus the
Company will receive an additional 1.5 million ounces of silver per
annum to be delivered by Goldcorp. Beginning August 6, 2014, Primero
will deliver to the Company a per annum amount equal to the first 6.0
million ounces of payable silver produced at San Dimas and 50% of any
excess, for the life of the mine.
|
|
11.
|
The Company's attributable tonnage at Pierina was estimated by assuming
2011 production level for the remaining two years. The Company's
attributable tonnage at Lagunas Norte and Veladero was estimated by
assuming 2012 and 2013 processed tonnes based on Barrick's life of mine
("LOM") plans. Tonnes for all three operations were pro-rated between
Proven and Probable Mineral Reserves according to the ratio of
Barrick's December 31, 2011 Proven and Probable Mineral Reserves.
Average reserve grades were applied to the Pierina estimates and the
average LOM plan grades were applied to Lagunas Norte and Veladero.
LOM plans and December 31, 2011 Mineral Reserves estimates are as
published by Barrick.
|
|
12.
|
The Company's Yauliyacu purchase agreement (March 2006) with Glencore
International AG provides for the delivery of up to 4.75 million ounces
of silver per year for 20 years. In the event that silver produced at
Yauliyacu in any year totals less than 4.75 million ounces, the maximum
amount to be sold to the Company in subsequent years will be increased
to make up the shortfall, so long as production allows. Depending upon
production levels it is possible that the Company's current
attributable tonnage may not be mined before the agreement expires.
|
|
13.
|
The Mineral Park and Rosemont Resources and Reserves do not include the
SX/EW leach material since this process does not recover silver.
|
|
14.
|
The Company's attributable tonnage at Cozamin was estimated by assuming
Capstone Mining Corp's (Capstone) 2012 production guidance of 1.1
million tonnes until the end of the Company's contract. Tonnes were
pro-rated between Proven and Probable Mineral Reserves according to the
ratio of Capstone's December 31, 2011 published Proven and Probable
Mineral Reserves, applying average reserve grades.
|
|
15.
|
The Company has filed a technical report for Yauliyacu, Peñasquito, San
Dimas and Pascua-Lama, which are available on SEDAR at www.sedar.com.
An updated technical report for San Dimas is expected to be filed on
SEDAR within 45 days. These four mineral assets are considered to be
material to the Company.
|
|
16.
|
Silver is produced as a by-product metal at all operations with the
exception of the Keno Hill mine and Loma de La Plata project;
therefore, the economic cut-off applied to the reporting of silver
Resources and Reserves will be influenced by changes in the commodity
prices of other metals at the time.
|
CAUTIONARY LANGUAGE REGARDING RESERVES AND RESOURCES
For further information on Mineral Reserves and Mineral Resources and on
Silver Wheaton more generally, readers should refer to Silver Wheaton's
Annual Information Form for the year ended December 31, 2011, and other
continuous disclosure documents filed by Silver Wheaton since January
1, 2012, available on SEDAR at www.sedar.com. Silver Wheaton's Mineral Reserves and Mineral Resources are subject to
the qualifications and notes set forth therein. Mineral Resources which
are not Mineral Reserves do not have demonstrated economic viability.
Cautionary Note to United States Investors Concerning Estimates of
Measured, Indicated and Inferred Mineral Resources: The information contained herein uses the terms "Measured", "Indicated"
and "Inferred" Mineral Resources. United States investors are advised
that while such terms are recognized and required by Canadian
regulations, the United States Securities and Exchange Commission does
not recognize them and expressly prohibits U.S. registered companies
from including such terms in their filings with the SEC. "Inferred
Mineral Resources" have a great amount of uncertainty as to their
existence, and as to their economic and legal feasibility. It cannot be
assumed that all or any part of an Inferred Mineral Resource will ever
be upgraded to a higher category. Under Canadian rules, estimates of
Inferred Mineral Resources may not form the basis of feasibility or
other economic studies. United States investors are cautioned not to
assume that all or any part of Measured or Indicated Mineral Resources
will ever be converted into Mineral Reserves or that any exploration
potential will ever be converted to any category of Mineral Reserves or
Mineral Resources. United States investors are also cautioned not to
assume that all or any part of an Inferred Mineral Resource exists, or
is economically or legally mineable. United States investors are urged
to consider closely the disclosure in Silver Wheaton's Form 40-F, a
copy of which may be obtained from Silver Wheaton or from http://www.sec.gov/edgar.shtml.
Mr.
Neil Burns
, Vice President of Technical Services, is a "qualified
person" as such term is defined under National Instrument 43-101, and
has reviewed and approved the contents of this news release.
About Silver Wheaton
Silver Wheaton is the largest silver streaming company in the world.
Based upon its current agreements, forecast 2012 attributable
production is approximately 27 million silver equivalent ounces,
including 16,500 ounces of gold. By 2016, annual attributable
production is anticipated to increase significantly to approximately 43
million silver equivalent ounces, including 35,000 ounces of gold. This
growth is driven by the Company's portfolio of world-class assets,
including silver streams on Goldcorp's Peñasquito mine and Barrick's
Pascua-Lama project.
CAUTIONARY NOTE REGARDING FORWARD LOOKING-STATEMENTS
The information contained herein contains "forward-looking statements"
within the meaning of the United States Private Securities Litigation
Reform Act of 1995 and "forward-looking information" within the meaning
of applicable Canadian securities legislation. Forward-looking
statements, which are all statements other than statements of
historical fact, include, but are not limited to, statements with
respect to the future price of silver and gold, the estimation of
mineral reserves and resources, the realization of mineral reserve
estimates, the timing and amount of estimated future production, costs
of production, reserve determination, reserve conversion rates and
statements as to any future dividends. Generally, these forward-looking
statements can be identified by the use of forward-looking terminology
such as "plans", "expects" or "does not expect", "is expected",
"budget", "scheduled", "estimates", "forecasts", "intends",
"anticipates" or "does not anticipate", or "believes", or variations of
such words and phrases or statements that certain actions, events or
results "may", "could", "would", "might" or "will be taken", "occur" or
"be achieved". Forward-looking statements are subject to known and
unknown risks, uncertainties and other factors that may cause the
actual results, level of activity, performance or achievements of
Silver Wheaton to be materially different from those expressed or
implied by such forward-looking statements, including but not limited
to: fluctuations in the price of silver and gold; the absence of
control over mining operations from which Silver Wheaton purchases
silver or gold and risks related to these mining operations including
risks related to fluctuations in the price of the primary commodities
mined at such operations, actual results of mining and exploration
activities, economic and political risks of the jurisdictions in which
the mining operations are located and changes in project parameters as
plans continue to be refined; and differences in the interpretation or
application of tax laws and regulations; as well as those factors
discussed in the section entitled "Description of the Business - Risk
Factors" in Silver Wheaton's Annual Information Form available on SEDAR
at www.sedar.com and in Silver Wheaton's Form 40-F on file with the U.S. Securities and
Exchange Commission in Washington, D.C. Forward-looking statements are
based on assumptions management believes to be reasonable, including
but not limited to: the continued operation of the mining operations
from which Silver Wheaton purchases silver or gold, no material adverse
change in the market price of commodities, that the mining operations
will operate and the mining projects will be completed in accordance
with their public statements and achieve their stated production
outcomes, and such other assumptions and factors as set out herein.
Although Silver Wheaton has attempted to identify important factors
that could cause actual results to differ materially from those
contained in forward-looking statements, there may be other factors
that cause results not to be as anticipated, estimated or intended.
There can be no assurance that forward-looking statements will prove to
be accurate. Accordingly, readers should not place undue reliance on
forward-looking statements. Silver Wheaton does not undertake to update
any forward-looking statements that are included or incorporated by
reference herein, except in accordance with applicable securities laws.